Welfare facilities on construction sites
Contents |
[edit] Introduction
There is a legal duty under The Workplace (Health, Safety and Welfare) Regulations 1992, as amended by The Construction (Design and Management) Regulations (CDM Regulations) to ensure that appropriate and adequate welfare facilities are provided at most workplaces.
The provision of welfare facilities should be considered at the planning stages of a project to ensure they are appropriately located.
The CDM regulations require that contractors, as far as is reasonably practicable, provide welfare facilities which meet the minimum requirements set out in Schedule 2 of the regulations for their own employees working on site or anyone else working under their control.
On projects where there is more than one contractor, the client and the principal contractor have a similar duty to ensure suitable and sufficient welfare facilities are provided for before any construction work starts and for the duration of the construction work. The principal contractor should liaise with other contractors involved in the project to ensure appropriate welfare facilities are provided. This should continue throughout the construction phase to take account of any changes which might change the requirement for the provision of welfare facilities.
Schedule 2 of the regulations suggests that the minimum welfare facilities required includes:
- Sanitary conveniences
- Washing facilities
- Drinking water
- Changing rooms and lockers
- Facilities for rest.
[edit] Sanitary conveniences
Clean and tidy toilets (sanitary conveniences) should be provided at easily accessible locations. They should have adequate ventilation and lighting. Ideally, separate male and female toilets should be provided but if this is not possible, as a minimum, rooms with lockable doors are required.
[edit] Washing facilities
Clean and tidy washing facilities with sufficient ventilation and lighting are required next to both toilets and changing areas with the following:
- Hot and cold running water.
- Soap or other cleaning agents.
- Towels or another method for drying hands.
- Showers may be required depending on the nature of the works.
Ideally, separate male and female facilities should be provided but if this is not possible, as a minimum, rooms with lockable doors are required.
[edit] Drinking water
An adequate supply of suitably signed drinking water is required, with suitable cups or other drinking vessels, unless the supply of drinking water is in a jet from which can be drunk easily.
[edit] Changing rooms and lockers
If employees are required to change into specialist clothing, separate male and female changing facilities are required with seating and secure areas for storing personal clothing and protective clothing. In addition facilities for drying wet clothing are required.
[edit] Rest facilities
Adequately heated rest facilities with the appropriate number of seats and tables are required, along with a method for heating drinks and warming food. Where necessary, they should include suitable facilities for a pregnant woman or a nursing mother to rest lying down.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.
Construction Management, 17 June
Government rolls out digital planning tool to all local authorities.
Your views needed - a strategy for the professions, trades and occupations.
Confronting competency, codes, capacity and costs.
The hidden risk in modern construction supply chains.
Construction Management, 10 June
24 months to 14: CITB launches accelerated apprenticeships.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.